06/12/2026
A progress update and historical trivia.
Leveling and repairing of cracks in hallway floors has been completed, and hallways are ready for new flooring to begin being installed next week. Lighting upgrades are well underway in the elementary and music hallways. Painting continued in the cafe, with the ceiling painting complete. In the gym, bleachers and basketball hoops were removed, and the room prepped for work to begin next week. Painting will occur first before new practice hoops and bleachers are installed, as well as a drop-down dividing curtain to allow the gym to be used as two separate spaces during the school day. Outside, roofing is complete on the maintenance garage and bus garage, and roofing is about 25% complete on the bus shed.