07/14/2026
Town Paving Program Update
Fiscal Year 2026 Completed Work
During fiscal year 2026, the town completed approximately 4.4 miles of roadway resurfacing. This work included:
Hampden Road, approximately 2.97 miles
An asphalt overlay on approximately 1,500 feet, or 0.28 mile, of the worst section of Gulf Road
Edgewood Street, approximately 1 mile
Clinton Street, approximately 0.1 mile
Replacement of the Edgewood Street sidewalk
Milling and paving have been completed on Clinton Street and Edgewood Street. Some final work remains, including backfilling along the newly replaced sidewalk and completing driveway aprons where needed.
Fiscal Year 2027 Planned Work
Colburn Road is scheduled to be milled beginning around August 13, 2026, or during the week of August 13, with paving to follow shortly afterward.
The Colburn Road project covers approximately 1.58 miles between Route 19 and Hydeville Road. The project will also include minor repairs to the Colburn Road Bridge near Route 19 and completion of the small section of Upper Road between Colburn Road and the abandoned Upper Road bridge.
Colburn Road will be completed through the State of Connecticut’s vendor-in-place paving contract. The current estimated cost of the project is approximately $500,000.
Between the work completed during fiscal year 2026 and the planned resurfacing of Colburn Road, the town will have addressed approximately 5.9 miles of roadway. This total does not include the additional small section of Upper Road.
Future Paving Program
The town is currently completing an updated pavement evaluation of roads throughout Stafford. The evaluation will be used to develop short- and long-term resurfacing and reconstruction plans, including one-year, three-year, five-year, and ten-year priorities.
The paving program will be based on current roadway conditions, traffic use, available external funding, and the amount allocated for paving each fiscal year. Once the pavement evaluation is complete, the Town will determine its paving priorities for the remainder of FY 2027
All paving schedules are subject to change due to weather, contractor availability, equipment issues, and other unforeseen conditions.