05/07/2026
Today, MTFR personnel traveled to Pierce Manufacturing in Bradenton, Florida to begin the final inspection process for our new engine.
Engine 66 was ordered in the spring of 2025 as part of a quick-delivery program and was partially funded through an LSA Statewide Grant. The new engine will feature a 2,000 GPM pump, 750-gallon water tank, low hosebed design, Whelen emergency lighting, FireTech HiViz scene lighting, a short overall wheelbase/length for improved maneuverability, and seating for six firefighters.
Engine 66 is expected to be delivered within the next month and will then undergo additional pre-delivery inspections, decal installation, and equipment/tool mounting. The engine is currently projected to be placed into service in late summer 2026.