08/31/2026
Jail Work Center Expansion Update 🚧
• Interior work is moving forward with MEP overhead installations, framing, drywall, and painting now underway.
• Exterior building trim is complete, and glazing is scheduled to begin this month.
• The covered walkway and exterior trim are officially wrapped up.
• Sitework is making great strides with sidewalks, high‑security fencing and gates, irrigation nearing completion, and landscaping well underway.
Each milestone brings us one step closer to a fully completed and functional space. More updates to come!