West Side Project Construction Activity Summary
9/4/2026 Completed & In-Progress Work:
7th Street and Elm Avenue:
- The first level of pavement has been completed. The second layer will occur later this year.
- The contractor will be working on areas behind the curb to finalize clean up efforts.
- Paving of driveway entrances will occur soon. Contractor is circling back with sub-contractor for an exact date.
- Hydo-seeding for grass has been completed. The new turf will require your assistance to ensure proper long-term growth. The Contractor will assist in watering initially, but ultimately it will be the responsibility of the property owner. Once the grass reaches a growth height of about 3-4 inches, please mow the newly established areas. Your assistance with re-establishing turf is greatly appreciated.
Lake May Drive & Road:
- Street grading work on the Lake May Drive & Road segment is complete. Concrete curb and gutter installation will take place on September 3 - 4. Please make sure your vehicle is out of your driveway prior to the placement of the concrete curbing. If your vehicle is in your driveway following placement of the concrete, it may be “trapped” for several days before you are able to move it out over the curbing. A good indication that concrete curbing is soon to be placed is when the contractor starts placing large metal stakes along the edge of the roadway to hold the stringline in place. Placement of concrete driveway entrances will happen in the next couple of weeks.
- The first layer of street pavement should begin in mid-September.
Garden Street:
- Grading work is completed on the segment of Garden Street from Walker Bay Blvd to Hwy 371. Concrete curb installation will take place on September 3 - 4. Please make sure your vehicle is out of your driveway prior to the placement of the concrete curbing. If your vehicle is in your driveway following placement of the concrete, it may be “trapped” for several days before you are able to move it out over the curbing. A good indication that concrete curbing is soon to be placed is when the contractor starts placing large metal stakes along the edge of the roadway to hold the stringline in place. Placement of concrete driveway entrances will happen in the next couple of weeks.
- The first layer of street pavement should begin in mid-September.
Michigan Avenue:
- Underground utility installation has been completed.
- Street grading work is completed. Concrete curb installation will take place on September 3 – 4. Please make sure your vehicle is out of your driveway prior to the placement of the concrete curbing. If your vehicle is in your driveway following placement of the concrete, it may be “trapped” for several days before you are able to move it out over the curbing. A good indication that concrete curbing is soon to be placed is when the contractor starts placing large metal stakes along the edge of the roadway to hold the stringline in place. Placement of concrete driveway entrances will happen in the next couple of weeks.
Hwy 371:
- The segment of watermain installation on the south side of Hwy 371 from Tianna Drive to 500' westerly has been completed with the exception of final clean-up efforts.
- Hydro-seeding for grass and other final clean-up efforts will occur soon.
*************************************************************************************
Please note: construction schedules and project timelines can change frequently due to various timing factors including weather. Updates will be provided as timelines change.
The City of Walker understands that a construction project can create inconveniences, and we appreciate your patience and understanding during the process. The construction staff will try to make the project run as smoothly as possible by addressing your needs and concerns in a timely manner.
*************************************************************************************
Contact Information:
Chris Thorson – Project Engineer
218-850-0153
[email protected]
Brad Niemela – Onsite Inspector
218-821-1957
Eric Guse – Contractor Superintendent
Kuechle Underground
320-342-6027
Chuck Geislinger – Project Manager
Kuechle Underground
320-493-9205
*************************************************************************************
More information related to the project can be found at www.ci.walker.mn.us and clicking on “West Side Project.”