Wisconsin I-94 East-West Project

Wisconsin I-94 East-West Project Contact information, map and directions, contact form, opening hours, services, ratings, photos, videos and announcements from Wisconsin I-94 East-West Project, Government Organization, 141 NW Barstow Street, Waukesha, WI.

The Wisconsin Department of Transportation
(WisDOT) will rebuild I-94 between 70th Street and 16th Street in Milwaukee County to replace aging infrastructure and improve safety
through modernized design and reduced congestion.

06/11/2026

Safety remains WisDOT’s top priority. Recently, the I-94 East-West project team hosted its inaugural safety event, recognizing the shared commitment to safety across the corridor. Thank you to all the contractors, crews, law enforcement officers, and first responders who work every day to help keep this project moving safely for workers, motorists, and the traveling public.

ICYMI: Eric Hanson, WisDOT Project Manager, was onsite with CBS 58 to discuss the steel sheet piling for the future reta...
06/09/2026

ICYMI: Eric Hanson, WisDOT Project Manager, was onsite with CBS 58 to discuss the steel sheet piling for the future retaining wall along eastbound I-94 in the cemetery section. The steel sheet piling wall will span approximately 843 feet, with steel sheets ranging from 19 to 27 feet deep that are hydraulically pressed into place.

MILWAUKEE (CBS 58) -- A major construction project along I-94 is wrapping up its latest phase that's focusing on protecting one of Milwaukee's most historic sites.In order to expand the interstate, the

CommuteWISE is Southeastern Wisconsin’s transportation demand management (TDM) program. The Southeastern Wisconsin Regio...
06/05/2026

CommuteWISE is Southeastern Wisconsin’s transportation demand management (TDM) program. The Southeastern Wisconsin Regional Planning Commission (SEWRPC) provides tools, subsidies, and expertise to empower individuals and employers to expand travel choices beyond driving alone.

Skip the Drive and get rewarded during the June Challenge!

Start today! Download our CommuteWISE mobile app or visit our website at connect.commutewise.org.

06/04/2026

🚧 CONSTRUCTION UPDATE 🚧

Major progress has been made on the 27th Street bridge, just south of I-94.

Crews have:
✅ Removed the concrete bridge deck
✅ Removed the steel bridge girders
✅ Demolished the bridge piers

Over the next several months, the 27th Street bridge will be reconstructed to accommodate the future expansion of I-94 East-West and the additional lanes planned as part of the project.

Stay tuned for more construction updates as work continues!

05/27/2026

🚧 CONSTRUCTION UPDATE 🚧

Last week, crews placed concrete girders along westbound I-94 over 64th Street as part of the temporary widening of the I-94 westbound lanes.

These girders previously carried traffic on John Nolen Drive over the Monona Causeway in Madison and are now getting a second life here on the I-94 East-West project.

🔹 7 girders installed
🔹 Lengths range from 35 feet to 65 feet
🔹 Temporary widening is expected to remain in place through summer 2028

The temporary bridge widening is a key step that will allow both eastbound and westbound I-94 traffic to continue moving while crews build the new eastbound I-94 lanes and bridges.

Reusing bridge materials helps keep the project moving efficiently while putting valuable infrastructure back to work in a new location.

🇺🇲 MEMORIAL DAY WORK RESTRICTIONS 🇺🇲Entering into the holiday weekend, all freeway work will be suspended from noon toda...
05/22/2026

🇺🇲 MEMORIAL DAY WORK RESTRICTIONS 🇺🇲

Entering into the holiday weekend, all freeway work will be suspended from noon today through 6 a.m. Tuesday morning, May 26. In our freeway work zones, at least two lanes will be open in each direction, with no overnight closures scheduled.

🚧 UPCOMING TRAFFIC IMPACTS 🚧Girder setting along the West Leg, at 64th Street, and bridge pier demolition on the Early E...
05/18/2026

🚧 UPCOMING TRAFFIC IMPACTS 🚧

Girder setting along the West Leg, at 64th Street, and bridge pier demolition on the Early East Leg, at 27th Street, will require overnight full closures of I-94 East-West on Wednesday, May 20.

⛔ I-94 eastbound and westbound will be closed between the Zoo Interchange and the Marquette Interchange overnight Wednesday, May 20.
🕙 Wednesday night's closures will be from 10 p.m. to 5 a.m. Please note that system ramps and service ramps may close up to 30 minutes prior to the start of the full closure.
➡️ Detour routes are shown on the map below.
🧹 Cleanup of freeway lanes and shoulders will also take place during these closures.

🚧 CONSTRUCTION UPDATE 🚧Daytime demolition operations are underway for the section of the 27th Street bridge extending ap...
05/15/2026

🚧 CONSTRUCTION UPDATE 🚧

Daytime demolition operations are underway for the section of the 27th Street bridge extending approximately 500 feet south of I-94. Over the next week, crews will complete demolition of this section by removing steel girders and bridge piers.

🔗 To stay up-to-date on the latest project information, visit our project website https://www.94eastwest.wisconsindot.gov/

🚧 CONSTRUCTION UPDATE 🚧Crews have begun installing the steel sheet piling for the future retaining wall along eastbound ...
05/11/2026

🚧 CONSTRUCTION UPDATE 🚧

Crews have begun installing the steel sheet piling for the future retaining wall along eastbound I-94 in the cemetery section. The steel sheet piling wall will span approximately 843 feet, with steel sheets ranging from 19 to 27 feet deep that will be hydraulically pressed into place.

Sheets are hydraulically pressed in with specialized equipment, minimizing vibrations in sensitive areas. This pressed in method also helps minimize noise and environmental impacts.

These permanent support systems play a critical role in maintaining safe excavation areas and keeping construction moving forward as the eastbound lanes are reconstructed.

🚧 CONSTRUCTION UPDATE 🚧Progress is happening behind the scenes to keep traffic moving during future construction stages....
05/07/2026

🚧 CONSTRUCTION UPDATE 🚧

Progress is happening behind the scenes to keep traffic moving during future construction stages.

Crews are currently driving bridge piles to prepare for temporary widening of the I-94 westbound bridge over 64th Street. Similar work will take place soon at 68th and 70th Streets, all part of a plan to safely shift traffic and allow bi-directional travel on I-94 westbound in future stages.

🔩 At 64th Street:
• 12 steel bridge piles installed
• Average length: ~60 feet
• Diameter: 10–14 inches

These deep foundations are a key step in building the temporary support needed to keep lanes open while construction continues.