02/16/2024
We encourage folks to attend/tune in to the February 20, 2024 Selectboard meeting for an update from MassDOT on the two Rt 6 projects commencing concurrently in Wellfleet. Below please find a summary based on project schedules received thus far (Please note that these projects have to comply with the summer construction moratorium so no work will be conducted from Memorial Day to Labor day although we may seek approval to conduct work in June to maintain project momentum):
(First project) Rt 6/Main Street Intersection Project (607397-122605) Way 68 to Main Street Intersection including a segment past the intersection to just beyond Seaman's Bank
Winter/Spring 2024 - Construction will commence with smaller tasks such as the installation of advanced warning signs and message boards. Tree protection and erosion controls will be implemented. Also, crews will begin to prune, clear and grub areas along Main street and Rt 6 to prepare for roadway work. I don't anticipate major traffic impediments or lane closures during this phase, although that is subject to change.
Fall 2024 - Spring 2026 - More substantial work will commence including the headwall/tide gate replacement on Main street. The installation and/or relocation of various underground/overhead utilities will begin with a heavy focus on drainage infrastructure which could lead to traffic delays and/or lane closures/detours. The utility work will continue until the Spring of 2026. Expect traffic delays during this phase, including but not limited to lane closures, alternating traffic lanes and detours.
Spring 2026 - Fall 2031 - This phase will include roadway reconstruction, sidewalk/curbs and shoulder work and traffic signal replacement. With ultimate project closeout anticipated late Fall of 2031. Expect traffic delays during this phase, including but not limited to lane closures, alternating traffic lanes and detours.
(Second Project) Rt 6 Pavement Preservation Project (609098-124020) Eastham/Wellfleet Town Line to Way 68
Winter/Spring 2024 - Construction will commence with the installation of advanced warning signs and message boards. Underground/overhead utilities will be installed or relocated as necessary. Drainage infrastructure will also be installed. Expect traffic delays during this phase, including but not limited to lane closures, alternating traffic lanes and detours.
Fall 2024 - Spring 2025 -3 Rapid flashing beacons will be installed at Wellfleet Cinemas, Old County Road and Cove Road. Expect traffic delays during this phase, including but not limited to lane closures, alternating traffic lanes and detours.
Spring 2025 - Fall 2026 - This phase will include roadway reconstruction, sidewalk/curbs and shoulder work. With ultimate project closeout anticipated late Fall of 2026. Expect traffic delays during this phase, including but not limited to lane closures, alternating traffic lanes and detours.
Please also be advised that these are estimated dates that are subject to change. If you have any other questions please feel free to contact the DPW at 508-349-0315