06/08/2026
DONICA ROAD WEEKLY UPDATE
Here’s a summary of the work completed June 1-5 on the Donica Road sewer project:
INSTALLATION
A new manhole on Donica Road was completed and several new service connections were installed which will serve existing and future properties along Donica Road.
EXCAVATION AND PIPE INSTALLATION
Crews installed 250 linear feet of new 8-inch gravity sewer main.
DRILLING AND BLASTING PREPARATION
Controlled blasting operations were conducted throughout the week in coordination with Capital Drilling & Blasting. All blasting activities were monitored using seismic and audible monitoring equipment, and the work proceeded as planned.
KEY MILESTONE:
250 linear feet of new 8-inch gravity sewer main was installed.
FIELD ISSUES
Despite significant ledge conditions, crews made excellent progress.
TRAFFIC AND SAFETY
Brief road closures and blasting operations occurred.
WHAT’S NEXT FOR JUNE 8-12
Construction activities will continue this week along with temporary road closures within the active work zone. Access to homes and businesses will continue to be maintained throughout the construction process. BLASTING WILL CONTINUE THIS WEEK.
SCHEDULE
Construction is continuing to stay on track and according to schedule.