08/31/2026
DONICA ROAD WEEKLY UPDATE
Hereâs a summary of the work completed August 24-28 on the Donica Road sewer project:
INSTALLATION This past week, the project continued moving through the final stages of major construction, with significant progress on the pump station and manhole/sewer main testing. Crews also began construction of a new 6-inch gravity sewer main behind Camden National Bank and finished by the end of the week.
PUMP STATION Albanese continued grading and installation of the gravel base and constructed the concrete pad for the new standby generator. Richardson Electric also continued electrical work associated with the pump station, including installation of the grounding system and final underground conduits.
KEY MILESTONE:
Successful pressure testing of the new 4-inch force main. The line was pressurized to 150 psi for two hours and successfully passed testing, allowing this major component of the new system to be accepted.
FIELD ISSUES
As is often with the case when working around older commercial properties, crews encountered several existing utilities that were either inaccurately marked or not previously documented, including water, propane, electrical, drainage, and other utility lines. One water service was damaged during excavation but was immediately repaired, and the affected facilities were flushed and returned to normal operation the same day.
TRAFFIC AND SAFETY
As construction continues, residents should continue to expect weekday construction activities, construction equipment, and occasional temporary traffic impacts within the work zone.
WHATâS NEXT FOR AUGUST 31 - SEPTEMBER 4
The remaining work will increasingly focus on completion and startup of the new pump station, final electrical work, site grading and restoration, roadway work, and development of the final project punch list. We will also be coordinating with the Town regarding the remaining reclaiming and paving work on Donica Rd.
SCHEDULE
The project has come a long way since construction began, and we are now approaching the point where the focus shifts from installing major infrastructure to completing, testing, restoring, and preparing the new system for operation.