York Sewer District

York Sewer District The York Sewer District's mission is to collect and treat wastewater generated in York, Maine

06/08/2026

DONICA ROAD WEEKLY UPDATE
Here’s a summary of the work completed June 1-5 on the Donica Road sewer project:
INSTALLATION
A new manhole on Donica Road was completed and several new service connections were installed which will serve existing and future properties along Donica Road.
EXCAVATION AND PIPE INSTALLATION
Crews installed 250 linear feet of new 8-inch gravity sewer main.
DRILLING AND BLASTING PREPARATION
Controlled blasting operations were conducted throughout the week in coordination with Capital Drilling & Blasting. All blasting activities were monitored using seismic and audible monitoring equipment, and the work proceeded as planned.
KEY MILESTONE:
250 linear feet of new 8-inch gravity sewer main was installed.
FIELD ISSUES
Despite significant ledge conditions, crews made excellent progress.
TRAFFIC AND SAFETY
Brief road closures and blasting operations occurred.
WHAT’S NEXT FOR JUNE 8-12
Construction activities will continue this week along with temporary road closures within the active work zone. Access to homes and businesses will continue to be maintained throughout the construction process. BLASTING WILL CONTINUE THIS WEEK.
SCHEDULE
Construction is continuing to stay on track and according to schedule.


06/01/2026

DONICA ROAD UPDATE
Albanese will be back on Donica Road today and will start blasting for the pipe trench and will continue throughout the week.

05/17/2026

DONICA ROAD WEEKLY UPDATE

Crews have finished work on Route 1. Sewer main and manholes have been installed as well as paving complete. Crews will be taking a 2 week pause as they head to another project. They will return to Donica Road on June 1st.

DONICA ROAD WEEKLY UPDATEHere’s a summary of the work completed May 4-8 on the Donica Road sewer project:INSTALLATION Cr...
05/11/2026

DONICA ROAD WEEKLY UPDATE
Here’s a summary of the work completed May 4-8 on the Donica Road sewer project:
INSTALLATION
Crews continued utility installation operations on Route 1 in the vicinity of Donica Road and Anthony’s. Work included re-excavation and completion of 2 manholes, installation of associated 8” PVC gravity sewer and the 6” force main piping, installation of a new 6” PVC sewer service at Anthony’s and continued tie-in work at the directional drill receiving pit near Donica Road. Additional gravity sewer and force main piping were also installed between the Route 1 work area and Donica Road directional drill location.
KEY MILESTONE:
Installation of 2 manholes on Route 1
In addition, installation of 8” gravity sewer and 6” force main. Installation of 6” sewer service at Anthony’s. Gravity sewer and force main were also installed between Route 1 and Donica Road.
FIELD ISSUES
No field issues
TRAFFIC AND SAFETY
Traffic impacts were minimal and traffic control will continue during active construction operations. Motorists should continue to expect lane shifts, steel plates, uneven pavement, and minor delays in the work zone. Police details and traffic control personnel will remain onsite during active work hours to maintain safe traffic flow.
WHAT’S NEXT FOR MAY 11-15
Beginning Tuesday, Albanese is expected to begin roadway preparation activities on Route 1, including milling and temporary surface preparation, with paving operations anticipated to follow and likely continue into Wednesday. A Wirtgen milling machine was delivered in preparation for this week.
Crews also plan to continue the installation of the 8” gravity sewer and 6” force main at Route 1 and Donica with the installation of another manhole anticipated later this week pending field conditions and coordination with the engineer.
SCHEDULE
Construction is continuing to stay on track and according to schedule.


See less

DONICA ROAD WEEKLY UPDATEHere’s a summary of the work completed April 27-May 1 on the Donica Road sewer project:INSTALLA...
05/04/2026

DONICA ROAD WEEKLY UPDATE
Here’s a summary of the work completed April 27-May 1 on the Donica Road sewer project:
INSTALLATION
Crews continued installation of the new sewer main and service wyes on Donica Road including related service connections between Manhole 1410 and Manhole 1411.
EXCAVATION AND PIPE INSTALLATION Conditions have been favorable, with dry and gravelly soils, though some areas included weathered ledge, isolated groundwater seepage at depth, several boulders requiring removal, and multiple water services that were pneumatically exposed and coordinated with York Water District.
DRILLING AND BLASTING PREPARATIONS No update given this week.
KEY MILESTONE:
Several service wyes were installed for Donica Road properties.
Service wyes were installed for lots 18, 19, 20, 21, 22, 23, 24 and 25.
FIELD ISSUES
Storm Drain Culvert. A deteriorated 15-inch storm drain culvert was uncovered, found to be partially corroded, removed, and temporarily repaired with sleeved 8-inch PVC. York Public Works was notified.
TRAFFIC AND SAFETY
Traffic impacts were minimal with no police details required during this phase. “Road Closed” signage continues to be in place, limiting through traffic while maintaining local access.
WHAT’S NEXT FOR MAY 4-8
Crews have mobilized back to Route 1 to complete installation of that portion of the sewer. This work is expected to take approximately 2-3 weeks, including paving.
SCHEDULE
Construction is continuing to stay on track and according to schedule.



DONICA ROAD WEEKLY UPDATEHere’s a summary of the work completed April 20-24 on the Donica Road sewer project:INSTALLATIO...
04/27/2026

DONICA ROAD WEEKLY UPDATE
Here’s a summary of the work completed April 20-24 on the Donica Road sewer project:
INSTALLATION
Crews advanced installation of the new sewer main up Donica Road including installation of several manholes. Crews have also been meeting directly with property owners to confirm service connection locations. This includes adjustments to better align with existing septic systems and services, helping to make future connections as straightforward as possible.
EXCAVATION AND PIPE INSTALLATION Conditions have been favorable, with dry and gravelly soils, though some areas included weathered ledge and previously disturbed material around existing utilities. The Team has been working closely with the York Water District to safely cross and protect water lines as installation progresses.
DRILLING AND BLASTING PREPARATIONS Drilling and blasting preparation has now been completed along Donica Road and in the areas behind Meadowbrook Plaza and along Eldredge Drive. Crews encountered some ledge and large boulders along the route, which were removed as needed to maintain progress.
KEY MILESTONE:
Daily progress has ranged from roughly 60 to over 120 feet of new sewer main installed on Donica Rd.
Successful installation of new sewer main completing multiple sections of pipe and installation of several manholes.
FIELD ISSUES
Manholes on Route 1 The manholes planned for Route 1 are still being finalized from an engineering standpoint to ensure they are constructed on a stable and reliable bases. Once that design is confirmed, crews will return to Route 1 to complete that portion of the work.
TRAFFIC AND SAFETY
Traffic impacts were minimal with no police details required during this phase. “Road Closed” signage continues to be in place, limiting through traffic while maintaining local access.
WHAT’S NEXT FOR APRIL 27-MAY 1
Crews plan to continue south along Donica Road and will keep coordinating with residents as crews approach individual properties.

Blasting notices will be provided in advance via email, yorksewerdistrict.org and on YSD’s Instagram and Facebook.



04/20/2026

DONICA ROAD WEEKLY UPDATE
Here’s a summary of the work completed April 13-17 on the Donica Road sewer project:

INSTALLATION
Crews advanced installation north on Route 1, completing additional sections of gravity sewer and force main, as well as continued preparation for upcoming trenching and blasting operations on Donica Road.

EXCAVATION AND PIPE INSTALLATION Subsurface conditions remain consistent with prior observations, including layers of pavement and granular fill overlying marine clay. Based on these conditions, the project team is coordinating with Woodard & Curran, S.W. Cole, and the contractor on the final design approach for the manholes. A proposal for helical pile support at these structures is currently under review.

DRILLING AND BLASTING PREPARATIONS Pre-drilling activities continued along Donica Road.

KEY MILESTONE:
Successful installation of gravity sewer between 2 manholes on Route 1 north of the culvert.
Placement and successful testing of one of the new manholes was done following field adjustments. Roadway subbase reconditioning in previously installed areas was done as well.

FIELD ISSUES
A mis-marked utility was struck during pre-drilling; the affected water service was repaired and restored the same day in coordination with the York Water District.

A deteriorated cross drain was identified and temporarily replaced, with follow-up coordination planned with the Town.

TRAFFIC AND SAFETY
Traffic impacts were minimal with only a slight lane shift in place; traffic continued to move smoothly through the area.

Public-related safety incidents there were two public-safety incidents that occurred within the work zone. Both were managed appropriately on site, with no injuries reported. These incidents reinforce the importance of adhering to posted traffic controls and detour routes.

All work areas were secured and plated at the end of each day to maintain safe conditions for both traffic and pedestrians

WHAT’S NEXT FOR APRIL 20-24
Crews plan to continue advancing along Donica Road while coordination continues on the manhole foundation approach. The contractor is scheduled to be off Monday.

Blasting notices will be provided in advance via email, yorksewerdistrict.org and on YSD’s Instagram and Facebook.



DONICA ROAD WEEKLY UPDATEHere’s a summary of the work completed April 6–13 on the Donica Road sewer project:INSTALLATION...
04/13/2026

DONICA ROAD WEEKLY UPDATE

Here’s a summary of the work completed April 6–13 on the Donica Road sewer project:

INSTALLATION Crews continued installing the new sewer infrastructure near Route 1, focusing on the area between manholes and working both north and south along the alignment. This included installation of gravity sewer pipe and force main, as well as preparation for upcoming trenching and blasting operations further up Donica Road.

Toward the end of the week, crews observed some settlement at one of the installed manholes. Engineers and geotechnical specialists are evaluating the area and developing a long-term solution before work continues in that section.

EXCAVATION AND PIPE INSTALLATION Crews began near the southern portion of the project and, as work progressed, they encountered challenging subsurface conditions, including areas of clay and groundwater. These conditions required additional support measures and careful installation techniques to ensure long-term stability of the system.

DRILLING AND BLASTING PREPARATIONS Crews were onsite performing subsurface probing and beginning preparations for controlled blasting. This work helps identify ledge and allows the team to plan for safe and efficient trenching as the project advances.

KEY MILESTONE:

Successful installation of sewer pipes beneath the large culvert near Route 1

Instead of excavating under the culvert—which could have posed additional risk—the team installed the pipes through protective sleeves. This approach minimized disruption and helped keep the project on schedule.

TRAFFIC AND SAFETY

Traffic impacts were minimal with only a slight lane shift in place; traffic continued to move smoothly through the area

All work areas were secured and plated at the end of each day to maintain safe conditions for both traffic and pedestrians

WHAT’S NEXT FOR APRIL 13–20

Crews plan to continue advancing the sewer installation along Route 1 while also progressing drilling and preparation for upcoming blasting operations on Donica Road.

Blasting notices will be provided in advance via email, yorksewerdistrict.org and on YSD’s Instagram and Facebook.



𝗗𝗢𝗡𝗜𝗖𝗔 𝗥𝗢𝗔𝗗 𝗪𝗘𝗘𝗞𝗟𝗬 𝗨𝗣𝗗𝗔𝗧𝗘Hello everyone,We are excited to share this week's progress on the sewer extension project and ...
04/06/2026

𝗗𝗢𝗡𝗜𝗖𝗔 𝗥𝗢𝗔𝗗 𝗪𝗘𝗘𝗞𝗟𝗬 𝗨𝗣𝗗𝗔𝗧𝗘

Hello everyone,

We are excited to share this week's progress on the sewer extension project and what you can expect in the coming week.

𝗪𝗼𝗿𝗸 𝗖𝗼𝗺𝗽𝗹𝗲𝘁𝗲𝗱 𝗟𝗮𝘀𝘁 𝗪𝗲𝗲𝗸

Crews made strong progress along Donica Road and Route 1, despite challenging weather conditions at times.
Key activities included:

- 𝗗𝗶𝗿𝗲𝗰𝘁𝗶𝗼𝗻𝗮𝗹 𝗗𝗿𝗶𝗹𝗹𝗶𝗻𝗴 beneath Route 1 for installation of underground piping minimizing disruption to the roadway.
- 𝗖𝗼𝗻𝘀𝘁𝗿𝘂𝗰𝘁𝗶𝗼𝗻 𝗼𝗳 𝗻𝗲𝘄 𝗺𝗮𝗻𝗵𝗼𝗹𝗲 near the Route1 intersection to support the new sewer system.
- 𝗜𝗻𝘀𝘁𝗮𝗹𝗹𝗮𝘁𝗶𝗼𝗻 of sections of both gravity sewer and force main piping.
- 𝗧𝗲𝘀𝘁 𝗣𝗶𝘁𝘀 these pits were completed to confirm existing underground utilities and ensure safe separation between systems.
- 𝗣𝗿𝗲𝗽𝗮𝗿𝗮𝘁𝗶𝗼𝗻 𝗪𝗼𝗿𝗸 along Donica Road, including excavation, setup of work zones, and delivery of materials.

Work areas were secured at the end of each day with steel plates and barriers to maintain safe travel for vehicles and pedestrians.

𝗪𝗵𝗮𝘁 𝘁𝗼 𝗘𝘅𝗽𝗲𝗰𝘁 𝗧𝗵𝗶𝘀 𝗪𝗲𝗲𝗸

Work will continue in the Route 1 Donica Road area with the following planned activities:

- 𝗖𝗼𝗻𝘀𝘁𝗿𝘂𝗰𝘁𝗶𝗼𝗻 activity will typically occur between 7:00 AM and 4:00 PM
- 𝗧𝗿𝗮𝗳𝗳𝗶𝗰 temporary lane shifts or minor delays may occur near the Route 1 intersection and along Donica Road
- 𝗡𝗼𝗶𝘀𝗲 some noise and vibration should be expected during drilling and excavation.
- 𝗔𝗰𝗰𝗲𝘀𝘀 to homes will be maintained, though brief delays may occur when crews are working directly in front of properties.

𝗬𝗼𝗿𝗸 𝗦𝗲𝘄𝗲𝗿 𝗗𝗶𝘀𝘁𝗿𝗶𝗰𝘁 𝗶𝘀 𝗰𝗼𝗺𝗺𝗶𝘁𝘁𝗲𝗱 𝘁𝗼 𝗰𝗹𝗲𝗮𝗿 𝗰𝗼𝗺𝗺𝘂𝗻𝗶𝗰𝗮𝘁𝗶𝗼𝗻𝘀 𝗮𝗻𝗱 𝗽𝗿𝗼𝗷𝗲𝗰𝘁 𝘁𝗿𝗮𝗻𝘀𝗽𝗮𝗿𝗲𝗻𝗰𝘆. For questions about the Donica Road project, process, construction phases or to learn more about how to connect your property to the new sewer extension, visit us online at yorksewerdistrict.org or email our team today at [email protected]



𝐃𝐎𝐍𝐈𝐂𝐀 𝐑𝐎𝐀𝐃 𝐖𝐄𝐄𝐊𝐋𝐘 𝐔𝐏𝐃𝐀𝐓𝐄Phase 1 Donica Road Sewer Extension Project construction begins the week of March 30 with four ...
03/31/2026

𝐃𝐎𝐍𝐈𝐂𝐀 𝐑𝐎𝐀𝐃 𝐖𝐄𝐄𝐊𝐋𝐘 𝐔𝐏𝐃𝐀𝐓𝐄

Phase 1 Donica Road Sewer Extension Project construction begins the week of March 30 with four major areas of work completed this spring by our construction partner Albanese D&S Inc. and their contractors:

𝐌𝐚𝐫𝐜𝐡 𝟑𝟎 - 𝐌𝐚𝐲 𝟐𝟗

- 𝐃𝐢𝐫𝐞𝐜𝐭𝐢𝐨𝐧𝐚𝐥 𝐛𝐨𝐫𝐢𝐧𝐠𝐬 for the gravity main, force main and Anthony’s service lateral under Route 1

- 𝐋𝐚𝐲𝐢𝐧𝐠 𝐭𝐡𝐞 𝐠𝐫𝐚𝐯𝐢𝐭𝐲 𝐬𝐞𝐰𝐞𝐫 𝐚𝐧𝐝 𝐟𝐨𝐫𝐜𝐞 𝐦𝐚𝐢𝐧 along the westernmost southbound lane on Route 1

- 𝐃𝐫𝐢𝐥𝐥𝐢𝐧𝐠 𝐟𝐨𝐫 𝐛𝐥𝐚𝐬𝐭𝐢𝐧𝐠 associated with the sewer trench on Donica Road. Anticipated times for blasting are during the week of April 12, updates will be provided. 𝑫𝒓𝒊𝒍𝒍𝒊𝒏𝒈 𝒓𝒆𝒒𝒖𝒊𝒓𝒆𝒔 𝒂 1-𝒍𝒂𝒏𝒆 𝒕𝒓𝒂𝒇𝒇𝒊𝒄 𝒑𝒂𝒕𝒕𝒆𝒓𝒏 𝒐𝒏 𝒘𝒆𝒆𝒌𝒅𝒂𝒚𝒔 7:00 𝑨𝑴 - 5:00 𝑷𝑴. Access from both ends of Donica Road will be available and will keep traffic impacts to minimum

- 𝐈𝐧𝐬𝐭𝐚𝐥𝐥𝐢𝐧𝐠 the sewer main and service laterals to the property line; additional updates will be provided in early May

𝐘𝐨𝐫𝐤 𝐒𝐞𝐰𝐞𝐫 𝐃𝐢𝐬𝐭𝐫𝐢𝐜𝐭 𝐢𝐬 𝐜𝐨𝐦𝐦𝐢𝐭𝐭𝐞𝐝 𝐭𝐨 𝐜𝐥𝐞𝐚𝐫 𝐜𝐨𝐦𝐦𝐮𝐧𝐢𝐜𝐚𝐭𝐢𝐨𝐧𝐬 𝐚𝐧𝐝 𝐩𝐫𝐨𝐣𝐞𝐜𝐭 𝐭𝐫𝐚𝐧𝐬𝐩𝐚𝐫𝐞𝐧𝐜𝐲. For questions about the Donica Road project, process, construction phases or to learn more about how to connect your property to the new sewer extension, visit us online at yorksewerdistrict.org or email our team today [email protected]

Address

21 Bay Haven Road
York, ME
03909

Alerts

Be the first to know and let us send you an email when York Sewer District posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Organization

Send a message to York Sewer District:

Share