Phase 2 construction for this week - October 19, 2026STOREY PARK NEIGHBORHOOD - South of Onaga Trail• AC Berm paving • C...
10/19/2026

Phase 2 construction for this week - October 19, 2026

STOREY PARK NEIGHBORHOOD - South of Onaga Trail
• AC Berm paving
• Concrete restoration
• Manhole raising

SKY HARBOR
• Mainline installation on Juarez Drive, Lisbon Drive, Desert Gold Drive, and Ivanhoe Drive
• Lateral installation on El Dorado Drive, Warren Vista Avenue, Juarez Drive, and San Diego Drive
• Mainline and Lateral Staking
• Grading for paving

Thank You for Visiting Hi-Desert Water District!Hi-Desert Water District would like to thank James DeLoera, Field Repres...
10/08/2026

Thank You for Visiting Hi-Desert Water District!

Hi-Desert Water District would like to thank James DeLoera, Field Representative for U.S. Senator Adam Schiff, for taking the time to visit our District today.

We appreciate the opportunity to discuss our community’s needs, provide updates on our Phase 2 Sewer Project, and share our future plans for the Groundwater Replenishment and Reuse Project.

These important projects represent our continued commitment to protecting local groundwater resources, improving infrastructure, and ensuring sustainable water for our future.

Thank you, James, for your interest and engagement. We value the opportunity to strengthen communication and collaboration with Senator Schiff’s office.

Water Professionals Appreciation Week is October 3-11, 2026.Celebrating the team behind the water. Every drop starts wit...
10/06/2026

Water Professionals Appreciation Week is October 3-11, 2026.
Celebrating the team behind the water. Every drop starts with dedicated staff. Thank you!

09/21/2026

📢 LOBBY HOURS UPDATE

Beginning tomorrow, Tuesday, September 22, 2026, the Hi-Desert Water District lobby will be closed daily from 12:00 PM to 1:00 PM.

Our regular lobby hours will resume each day at 1:00 PM.

We appreciate your understanding and thank you for your patience as we make this adjustment.

09/03/2026
https://cvcpl.us/j6TytUJ
08/17/2026

https://cvcpl.us/j6TytUJ

Please use extreme caution when driving through work areas. Plan ahead when traveling in construction areas, and prepare for traffic delays and detours. We appreciate your patience while our contractors complete this work safely.  

08/11/2026

Please use extreme caution when driving through work areas. Plan ahead when traveling in construction areas, and prepare for traffic delays and detours. We appreciate your patience while our contractors complete this work safely.  

Check out this week's sewer project construction update.
07/13/2026

Check out this week's sewer project construction update.

FOR IMMEDIATE RELEASEHard Road Closure Scheduled on Palomar Avenue Between Joshua Drive and Ute Trail
07/09/2026

FOR IMMEDIATE RELEASE
Hard Road Closure Scheduled on Palomar Avenue Between Joshua Drive and Ute Trail

Yucca Valley, CA — July 09, 2026 – The Hi-Desert Water District announces a hard road closure on Palomar Avenue between Joshua Drive and Ute Trail for sewer project construction. The closure will begin on Monday, July 13, at 7:00 a.m. and remain in effect through Wednesday, July 15, at 5:0...

Address

55439 29 Palms Highway
Yucca Valley, CA
92284

Opening Hours

Monday 7:30am - 5pm
Tuesday 7:30am - 5pm
Wednesday 7:30am - 5pm
Thursday 7:30am - 5pm

Telephone

(760) 365-8333

Alerts

Be the first to know and let us send you an email when Hi-Desert Water District posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Share