01/06/2026
Construction activities for the Ebeye Seawall PREP II Footpath Project continue to progress steadily along the ocean-side. Current efforts include site grading and surface preparation to enhance pedestrian access and establish a continuous pathway alignment along the seawall. Additionally, cast-in-place reinforced concrete sidewalk sections are in progress. Each concrete panel is constructed with embedded dowels to ensure a robust structural connection between adjacent spans, thereby improving load transfer and the overall performance of the footpath.
Funding for footpath is provided by KADA (compact fund), with an allocation of $2,450,000.00, to cover the shortfall of the WB PREP II project. We sincerely appreciate the support of the people and the Government of the United for addressing this shortfall.