Kwajalein Atoll Development Authority to provide programs and services to the Kwajalein landowner communities at Ebeye and other Marshallese communities within Kwajalein Atoll impacted by the presence of the United States on Kwajalein Atoll; to ensure better fiscal responsibility and accountability to the people of Kwajalein Atoll; and for other purposes:

Enebouj Community Center Project update. Preparatory work for the wall footing concrete pouring is currently underway, i...
22/07/2026

Enebouj Community Center Project update. Preparatory work for the wall footing concrete pouring is currently underway, including the fabrication and placement of rebar reinforcement. At the same time, the er****on of roof truss members is ongoing to prepare for the installation of roofing materials.







Today, after so long, JoeMar has started working on punchlist items (such as fixing the speed hump stormwater access and...
22/07/2026

Today, after so long, JoeMar has started working on punchlist items (such as fixing the speed hump stormwater access and clearing gutter and road debris) for the Ebeye to Enen Jabro Sidewalk Project.







Enebouj Community Center Project as of today. Big kommol to our contractor, RMI Builders. Photo credit to RMI Builders. ...
13/07/2026

Enebouj Community Center Project as of today. Big kommol to our contractor, RMI Builders.

Photo credit to RMI Builders.







The ADB Road and Drainage Improvement Project is gaining momentum! Installation of traffic signs and street names has st...
08/07/2026

The ADB Road and Drainage Improvement Project is gaining momentum! Installation of traffic signs and street names has started, marking a major milestone in enhancing road safety and ensuring a smoother, safer journey for everyone.







Yokwe Everyone!Let's give a warm welcome to our new intern, Ms. Faith L. Kabua, as she joins the KADA team. Laan will be...
06/07/2026

Yokwe Everyone!

Let's give a warm welcome to our new intern, Ms. Faith L. Kabua, as she joins the KADA team. Laan will be assisting us with administrative tasks until she returns to university in Taiwan next month. We are grateful to the National Training Council for providing Laan with this valuable opportunity to experience life beyond academics.

Welcome aboard, Laan!

Construction of the Ebeye Morgue block is under inspection as of 6/30/2026. Block laying has now begun, which will defin...
30/06/2026

Construction of the Ebeye Morgue block is under inspection as of 6/30/2026. Block laying has now begun, which will define the partitions and enclosure of the structure. We are carefully checking the layout, the block layers, and the reinforcement to ensure everything meets our standards. This crucial phase represents significant progress on the project.







Recently, JoeMar has been conducting cleaning activities at Onemak Outfall. The deployment of jetty equipment and the im...
25/06/2026

Recently, JoeMar has been conducting cleaning activities at Onemak Outfall. The deployment of jetty equipment and the implementation of debris push-off methods are still needed to fully unclog the system. Joemar is currently cleaning the drainage and catch basin located at the mid-corridor site. The cleaning of the manhole will come next; however, it is waiting for their forklift to arrive so they can proceed. Kommol tata JoeMar!







Update on ADB project: The installation of the flap valve for the outfalls is currently underway, beginning specifically...
22/06/2026

Update on ADB project: The installation of the flap valve for the outfalls is currently underway, beginning specifically at Outfall #6. This includes detailed procedures such as site preparation, valve assembly, and testing phases to ensure proper functionality and compliance with project standards.







Declogging of Outfall 7 at Onemak was performed using a jetting device as part of our comprehensive maintenance plan for...
22/06/2026

Declogging of Outfall 7 at Onemak was performed using a jetting device as part of our comprehensive maintenance plan for the road and drainage system in collaboration with JoeMar.







Update on the Ebeye Morgue project: concrete pouring has commenced for the slab that will serve as the finished floor le...
22/06/2026

Update on the Ebeye Morgue project: concrete pouring has commenced for the slab that will serve as the finished floor level, ensuring structural stability and proper elevation for subsequent construction phases.







Address

PO Box 5858
Ebeye
96970

Opening Hours

Monday 08:00 - 17:00
Tuesday 08:00 - 17:00
Wednesday 08:00 - 17:00
Thursday 08:00 - 17:00
Friday 08:00 - 17:00

Telephone

6923298008

Website

Alerts

Be the first to know and let us send you an email when Kwajalein Atoll Development Authority - KADA posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Shortcuts

Share