WEEKLY PROJECT UPDATE: CLARKSBURG WATER AND SEWER IMPROVEMENTS
Reporting Period: Week of June 8
Upcoming Schedule: June 15-19
Prepared by: Bobby Tenney, Construction Manager (The Thrasher Group)
NORTH VIEW – CLARKSBURG WATER BOARD
Contract No. 1 – Bear Contracting
The contractor completed installation of the new water main on Gould Avenue from 19th Street to 25th Street and on 20th Street and 21st Street from Williams Avenue to Hamill Avenue.
New customer meter services were installed behind the completed mainline installation. Sidewalk and yard restoration activities continued throughout the project area.
Milling and paving operations were completed on several streets between 12th Street and 16th Street, as well as on Ohio Avenue and West Virginia Avenue.
The schedule for next week is to continue installation of the new water main on Pride Avenue from 20th Street to 24th Street and install new customer meter services behind the mainline installation. The new waterline on Gould Avenue will be tied into 21st Street, 23rd Street, and 25th Street and will require temporary service interruptions Tuesday through Thursday.
NO PARKING signs will be placed in the sections where the contractor is scheduled to work. Residents are asked to find alternate parking during the posted work hours. If your vehicle is parked within the work zone, it will be relocated to a safe location if the owner cannot be contacted. If you need access to your driveway, please speak with the contractor on-site.
Pride Avenue will be closed from 20th Street to 24th Street. Gould Avenue will be closed in sections from 21st Street to 25th Street.
Road Closed signs will be in place. Please use alternate routes whenever possible.
Fire and EMS services in the North View area should not be affected this week.
HARTLAND AND STEALEY AREAS – CLARKSBURG WATER BOARD
Contract No. 2 – Doss Enterprises
New customer meter settings were installed on Duff Avenue, Joseph Street, Carpenter Street, Ridenour Street, Hall Street, Baver Street, and Stealey Avenue. Concrete sidewalk repairs and yard restoration activities continued throughout the project area. Trench paving also continued on streets where new meter service installations were completed. Installation of the new water main continued on Duff Avenue from Hall Street toward Carpenter Street.
The schedule for next week is to continue installing customer meter settings on Duff Avenue and complete customer service connections on Baver Street, Marion Street, and Stealey Avenue. The contractor will continue concrete repairs and yard restoration activities throughout the project area. Installation of the new water main will begin on Duncan Avenue from Duff Avenue to Collins Avenue.
NO PARKING signs will be placed in the sections where the contractor is scheduled to work. Residents are asked to find alternate parking during the posted work hours. If your vehicle is parked within the work zone, it will be relocated to a safe location if the owner cannot be contacted. If you need access to your driveway, please speak with the contractor on-site.
Marion Street, Baver Street, Stealey Avenue, and Duncan Avenue will be closed periodically throughout the week.
Road Closed signs and flaggers will be in place. Please use alternate routes whenever possible.
Fire and EMS services in the Stealey area surrounding the park should not be affected. Flaggers will be present in the work zone to allow local traffic to safely enter and exit the area.
CHESTNUT HILLS (KRAMER DRIVE) – CLARKSBURG WATER BOARD
Contract No. 3 – D&M Contracting
This project has been completed.
DOWNTOWN AREA – CLARKSBURG WATER BOARD
Contract No. 4W – Independent Enterprises
The contractor completed milling and paving operations on 3rd Street from Main Street to Pike Street and on Traders Alley from Chestnut Street to 4th Street.
This project has been completed.
DOWNTOWN AREA (WEST END) – CLARKSBURG SANITARY BOARD
Contract No. 4S – Independent Enterprises
The contractor completed all remaining punch list items, and this project is now complete.
We appreciate your continued patience and cooperation as we upgrade Clarksburg’s essential water and sewer infrastructure.
For more information or project-related questions, please contact the Construction Manager at (304) 288-8142.