05/10/2026
NORTH YORKSHIRE COUNCIL - Project Update: 15
Project: Royal Parade, Filey
Project Number: 25011
File: 6.0 Correspondence/6.9 Filey Town Council
Title: Filey Town Council – Fortnightly Update
Progress
Royal Parade, Filey - Project Update
Since update 14, internal high-level reviews have taken place within the Council to review the status of the project and to consider the potential options for the future of the site.
The Council is now progressing work to identify the most appropriate replacement solution for the site.
The options currently being developed will be presented corporately and to members for consideration and agreement on a preferred way forward.
Following consideration of the available options and agreement to progress, officers will present the proposals to stakeholders to
obtain feedback and ensure local views are considered as the project develops.
Alongside this, officers will continue direct engagement with existing tenants to better understand their operational requirements, concerns and aspirations for any replacement facility. This engagement is an important part of the project and will help inform future design development
Officers remain very aware of the ongoing concerns relating to the Yorkshire Water pumping station located within the site area.
We continue to engage directly with Yorkshire Water to better
understand the issues and explore how these can be addressed as part of any future proposals. As previously noted, the pumping station is owned, operated and maintained by Yorkshire Water, and
responsibility for its operation and maintenance therefore rests with them.
Planning permission remains in place for the demolition of the existing structure. However, demolition is not currently
programmed, and no date has been agreed. The building continues to be monitored, and demolition would only be brought forward if ongoing movement within the structure created concerns that made intervention necessary in the interests of public safety.
At present, the kiosk units remain open and operational, although the café remains closed.
The Council remains committed to keeping stakeholders informed of progress and will provide a further update following Executive's consideration of the replacement options and subsequent
stakeholder engagement.
Wider Project Activity
• Assessment of replacement and redevelopment options is nearing completion.
• Officers continue to work with Yorkshire Water to ensure any future proposals address the site's drainage and pumping station challenges.
• Any replacement facility will need to provide a resilient,
sustainable solution suitable for the coastal environment.
• Modern Methods of Construction (MMC) are being explored to help reduce construction
time, minimise disruption and improve programme certainty