Conversation shall follow rules of polite discourse. Treat others as you would expect to be treated. We expect conversation to follow the rules of polite discourse and ask that participants treat each other, as well as our employees, with respect. Messages containing inappropriate content or language will be removed at the discretion of the Town administration. Please email the Town Manager with questions or concerns. Facebook messages are not regularly monitored.

06/08/2026
06/08/2026

6/8 Downtown Project Schedule & Updates
For all construction related questions, including scheduling, please contact Project Inspector Kevin Hughes at (207) 385-5588

Stormwater – After being off island last week, JBI will be in the Downtown Parking Lot starting today and continuing throughout the week. There will be traffic control measures and limited parking so please keep that in mind when you are downtown! GO SLOW and BE AWARE OF YOUR SURROUNDINGS!

Boat Ramps – Approaches to both ramps are being paved starting tomorrow and continuing over the course of two+ days. During paving, each ramp will be temporarily inaccessible. Please contact Kevin Hughes for more specifics: (207) 385-5588

For Downtown Project Info, Updates, and Schedule go to https://www.townofvinalhaven.org/1276/Downtown-Project

Immediately following the Annual Town Meeting June 11, 2026, there will be a Special Town Meeting.
06/04/2026

Immediately following the Annual Town Meeting June 11, 2026, there will be a Special Town Meeting.

Annual Town Meeting is June 11, 2026, 6PM, and Smith-Hokanson Memorial Hall (School Auditorium)
06/04/2026

Annual Town Meeting is June 11, 2026, 6PM, and Smith-Hokanson Memorial Hall (School Auditorium)

06/03/2026

6/3 Downtown Project Schedule & Updates
For all construction related questions, including scheduling, please contact Project Inspector Kevin Hughes at (207) 385-5588

General Update – As mentioned in our Monday notice, JBI is not doing any construction this week. We thank them for their ongoing work and appreciate everyone’s patience and kindness with the crew. We will have an update on their schedule by Friday.

Boat Ramps – Approaches to both ramps will be paved next week weather depending. Please be prepared for paving over the course of two+ days starting June 9. During paving, each ramp will be temporarily inaccessible. Please contact Kevin Hughes for more specifics as next week approaches and plans are finalized: (207) 385-5588

For Downtown Project Info, Updates, and Schedule go to https://www.townofvinalhaven.org/1276/Downtown-Project

06/02/2026
06/02/2026

🗳️ REMINDER: Thursday, June 4, is the last day to request an absentee ballot. All ballots MUST be returned to the Town Office by 8pm on Tuesday, June 9 to be counted.

06/01/2026

6/1 Downtown Project Schedule & Updates
For all construction related questions, including scheduling, please contact Project Inspector Kevin Hughes at (207) 385-5588

General Update – This week JBI will be planning and working on water layout but not doing active construction. We thank them for their ongoing work and appreciate everyone’s patience and kindness with the crew. They are doing a great job!

Boat Ramps – Approaches to both ramps will be paved next week weather depending. Please be prepared for paving over the course of two+ days starting June 9. During paving, each ramp will be temporarily inaccessible. Please contact Kevin Hughes for more specifics as next week approaches and plans are finalized: (207) 385-5588

For Downtown Project Info, Updates, and Schedule go to https://www.townofvinalhaven.org/1276/Downtown-Project

5/29 11am Stormwater UpdateJBI is currently excavating near the Fish Plant Boat Ramp but will be moving down to near Oak...
05/29/2026

5/29 11am Stormwater Update

JBI is currently excavating near the Fish Plant Boat Ramp but will be moving down to near Oakes / Coop area to dig this afternoon. There will be single lane traffic at that location while they are excavating. Please use caution!

For Downtown Project Info, Updates, and Schedule go to https://www.townofvinalhaven.org/1276/Downtown-Project

For all construction related questions, including scheduling, please contact Project Inspector Kevin Hughes at (207) 385-5588

The Vinalhaven Downtown Project is a comprehensive infrastructure initiative aimed at enhancing the functionality and resilience of Main Street, spanning from the ferry terminal to Water Street.

5/28 Downtown Project Schedule & UpdatesStormwater System – JBI will continue with stormwater system work on West Main S...
05/29/2026

5/28 Downtown Project Schedule & Updates

Stormwater System – JBI will continue with stormwater system work on West Main Street. Today they will be near the Fish Plant Boat Ramp area.

There will be one lane traffic throughout the day. Please keep this in mind as you travel to and from the ferry and use caution when traveling near the construction.

For Downtown Project Info, Updates, and Schedule go to https://www.townofvinalhaven.org/1276/Downtown-Project

For all construction related questions, including scheduling, please contact Project Inspector Kevin Hughes at (207) 385-5588

The Vinalhaven Downtown Project is a comprehensive infrastructure initiative aimed at enhancing the functionality and resilience of Main Street, spanning from the ferry terminal to Water Street.

Address

19 Washington School Road
Vinalhaven, ME
04863

Opening Hours

Monday 8am - 5pm
Tuesday 8am - 5pm
Wednesday 8am - 5pm
Thursday 8am - 5pm
Friday 8am - 12pm

Telephone

+12078634471

Alerts

Be the first to know and let us send you an email when Town of Vinalhaven posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Organization

Send a message to Town of Vinalhaven:

Share