Conversation shall follow rules of polite discourse. Treat others as you would expect to be treated. We expect conversation to follow the rules of polite discourse and ask that participants treat each other, as well as our employees, with respect. Messages containing inappropriate content or language will be removed at the discretion of the Town administration. Please email the Town Manager with questions or concerns. Facebook messages are not regularly monitored.

08/31/2026

8/31 Downtown Project Schedule & Updates

Stormwater – JBI will be working down by the Fishermen's Coop again today. Expect single lane traffic at the constriction site. Please be mindful of traffic control and drive slowly over crosscuts and through the construction zone.

Roads and Sidewalks – The road extending from the Ferry Terminal to Windy Way will be reclaimed beginning in mid-September. This means the roadway will be all gravel until mid-October, when the first layer of pavement will be installed on the road and in the bank parking lot. The final layer of pavement and sidewalk construction will take place next spring. JBI anticipates shutting down construction for the winter by mid-November and resuming work in the spring.

For Downtown Project Info, Updates, and Schedule go to https://www.townofvinalhaven.org/1276/Downtown-Project

08/28/2026

8/28 Downtown Project Schedule & Updates

Stormwater – BI will be working down by the Fishermen's Coop and are planning to wrap up in that location early next week. Expect single lane traffic at the constriction site. Please be mindful of traffic control and drive slowly over crosscuts and through the construction zone.

Roads and Sidewalks – The road extending from the Ferry Terminal to Windy Way will be reclaimed beginning in mid-September. This means the roadway will be all gravel until mid-October, when the first layer of pavement will be installed on the road and in the bank parking lot. The final layer of pavement and sidewalk construction will take place next spring. JBI anticipates shutting down construction for the winter by mid-November and resuming work in the spring.

For Downtown Project Info, Updates, and Schedule go to https://www.townofvinalhaven.org/1276/Downtown-Project

08/27/2026

8/27 Downtown Project Schedule & Updates

Stormwater – JBI will be working down by the Fishermen's Coop and the Greet’s entrance of the Fish Plant Parking Lot, and are planning to wrap up in that location tomorrow or early next week at the latest. The crew is addressing dust control by spreading calcium chloride. Expect single lane traffic at the constriction site. Please be mindful of traffic control and drive slowly over crosscuts and through the construction zone.

Roads and Sidewalks – The road extending from the Ferry Terminal to Windy Way will be reclaimed beginning in mid-September. This means the roadway will be all gravel until mid-October, when the first layer of pavement will be installed on the road and in the bank parking lot. The final layer of pavement and sidewalk construction will take place next spring. JBI anticipates shutting down construction for the winter by mid-November and resuming work in the spring.

For Downtown Project Info, Updates, and Schedule go to https://www.townofvinalhaven.org/1276/Downtown-Project

08/26/2026

FROM THE HARBOR MASTER: Will the person who placed a 20x20 float with barrels on the backside of Carver's Harbor please contact the Harbor Master IMMEDIATELY at 701-2018

08/26/2026

8/26 Downtown Project Schedule & Updates

Stormwater – JBI will be working down by the Fishermen's Coop. Expect single lane traffic at that location and a possible detour through the Fish Plant lot. Please be mindful of traffic control and drive slowly over crosscuts and through the construction zone.

For Downtown Project Info, Updates, and Schedule go to https://www.townofvinalhaven.org/1276/Downtown-Project

08/25/2026
08/25/2026

8/25 Downtown Project Schedule & Updates

Water – JBI is pausing water main work for the time being and will wrap up parts of the stormwater project.

Stormwater – JBI will be working down between the Coop and FIEC across from the Fish Plant parking lot. Expect single lane traffic at that location and a possible detour through the Fish Plant lot. Please be mindful of traffic control and drive slowly over crosscuts and through the construction zone.

For Downtown Project Info, Updates, and Schedule go to https://www.townofvinalhaven.org/1276/Downtown-Project

08/24/2026

8/24 Downtown Project Schedule & Updates

Water – JBI is pausing water main work for the time being and will wrap up parts of the stormwater project.

Stormwater – JBI will be working down by the Coop and the Greet’s Eats entrance of the Fish Plant parking lot. Expect single lane traffic at that location and a possible detour through the Fish Plant lot. Please be mindful of traffic control and drive slowly over crosscuts and through the construction zone.

For Downtown Project Info, Updates, and Schedule go to https://www.townofvinalhaven.org/1276/Downtown-Project

08/21/2026

8/21 Downtown Project Schedule & Updates

Water – JBI is pausing water for the time being, in order to complete the stormwater project.

Stormwater – JBI will be working down by the Coop and the Greet’s Eats entrance of the Fish Plant parking lot again today and will be there next week as well. Expect single lane traffic at that location and a possible detour through the Fish Plant lot. Please be mindful of traffic control and drive slowly over crosscuts and through the construction zone.

For Downtown Project Info, Updates, and Schedule go to https://www.townofvinalhaven.org/1276/Downtown-Project

08/20/2026

8/20 Downtown Project Schedule & Updates

Water – JBI is pausing water work today, and likely for the next several days, in order to complete more aspects of the stormwater project.

Stormwater – JBI will be doing some test drilling for the stormwater project down by the Coop and the Greet’s Eats entrance of the Fish Plant parking lot. Expect single lane traffic at that location and a possible detour through the Fish Plant lot. Please be mindful of traffic control and drive slowly over crosscuts and through the construction zone.

For Downtown Project Info, Updates, and Schedule go to https://www.townofvinalhaven.org/1276/Downtown-Project

Address

19 Washington School Road
Vinalhaven, ME
04863

Opening Hours

Monday 8am - 5pm
Tuesday 8am - 5pm
Wednesday 8am - 5pm
Thursday 8am - 5pm
Friday 8am - 12pm

Telephone

+12078634471

Alerts

Be the first to know and let us send you an email when Town of Vinalhaven posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Organization

Send a message to Town of Vinalhaven:

Shortcuts

Share