11/02/2026
Oversized Load Movement Scheduled from Jay to Turners Island, Maine
Barnhart Crane & Rigging Project 190595 – Load #6
Jay, Maine – November 3, 2026
Residents and motorists are advised that Barnhart Crane & Rigging, in coordination with Maine DOT, Maine State Police, local law enforcement agencies, utility companies, and project stakeholders, will continue transporting oversized industrial equipment from Jay, Maine, to Turners Island, Maine as part of Project 190595.
The project team is pleased to report that Load #5 was successfully completed, and we sincerely thank local communities, municipalities, law enforcement agencies, utility partners, and motorists for their continued cooperation and support throughout these transport operations.
Load #6 Movement Schedule
Tuesday, November 3, 2026
Safety Meeting: 5:00 PM
Departure from Jay: 6:00 PM
Bridge Closure Operations: 7:00 PM
Destination: Gray, Maine
Wednesday, November 4, 2026
Safety Meeting: 8:30 PM
Departure from Gray: 9:00 PM
Bridge Closure Operations: 10:00 PM
Destination: Buxton, Maine
Thursday, November 5, 2026
Safety Meeting: 8:30 PM
Departure from Buxton: 9:00 PM
Bridge Closure Operations: 10:00 PM
Final Destination: Turners Island, Maine
Road Closure and Detour Information
Temporary roadway closures and detours will be required during each night of transport to facilitate jumper bridge operations necessary for the safe movement of the oversized load. Motorists should anticipate temporary route changes, traffic holds, and delays while crews install, utilize, and remove the jumper bridges.
Law enforcement officers, traffic control personnel, and project crews will be positioned throughout the route to assist motorists and maintain public safety.
Traffic Advisory
Motorists traveling along or near the route should anticipate:
Temporary road closures and signed detours
Rolling traffic delays and traffic holds
Slow-moving oversized load operations
Utility, es**rt, and support vehicle activity
Law enforcement-assisted traffic control
Reduced travel speeds in the vicinity of the convoy
Drivers are encouraged to allow additional travel time, remain alert, and follow all directions provided by law enforcement officers and traffic control personnel.
Barnhart Crane & Rigging and the project team appreciate the patience and support shown by residents, municipalities, utility partners, law enforcement agencies, and the traveling public. Their cooperation remains critical to the safe and successful completion of Project 190595.
Important Notice: All dates and times are subject to change due to weather, safety considerations, permitting requirements, equipment availability, or operational needs. Additional updates will be provided as necessary.